City of Austin permit data, updated 2026-11-24
Austin commercial finish-out and remodel permits, 2026
Source: City of Austin Open Data, Issued Construction Permits (commercial building permits issued from 2026-01-01 on), pulled 2026-11-24. Counts and medians only; no names, permit numbers or addresses.
The short answer
From January 1 to 2026-11-24, the City of Austin issued 1,450 commercial building permits for finish-outs, remodels, change of use, interior demo and similar interior work. The median time from application to issue ran from 3 days for interior demo to 143 days for finish-out. The tables below show permits by month, timing and size for each job type.
| Job type | Permits 2026 | Median days, applied to issued | Median SF | Our page |
|---|---|---|---|---|
| Finish-out | 332 | 143 | 4,604 | finish-out page |
| Interior demo | 191 | 3 | 4,857 | interior demo page |
| Change of use | 205 | 64 | 2,800 | change of use page |
| Office floor remodel | 396 | 49 | 3,567 | office floor remodel page |
| Corporate amenity | 93 | 83 | 3,818 | corporate amenity page |
| Healthcare | 84 | 64 | 2,032 | healthcare page |
| Restroom and ADA | 64 | 79 | 2,170 | restroom and ada page |
| Warehouse and industrial | 85 | 60 | 10,350 | warehouse and industrial page |
Median days are counted from the application date to the issue date on each permit. Square feet come from the remodel area on the permit; permits with no area are left out of that median. Job types are sorted from the permit description; roofing, signs, solar, telecom, fences, new buildings and full demolitions are left out.
Finish-out
332 permits in 2026; median 143 days from application to issue; median 4,604 square feet.
Permits by month
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov |
|---|---|---|---|---|---|---|---|---|---|---|
| 28 | 22 | 27 | 20 | 66 | 38 | 52 | 27 | 22 | 17 | 13 |
What this means if you are opening or renovating a space: Finish-out permits took the longest of these job types to issue. If you are opening a new suite, start the drawings and permit application early and plan the build start around the issue date, not the lease date. See our finish-out page.
Interior demo
191 permits in 2026; median 3 days from application to issue; median 4,857 square feet.
Permits by month
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov |
|---|---|---|---|---|---|---|---|---|---|---|
| 19 | 15 | 20 | 15 | 16 | 35 | 13 | 17 | 14 | 11 | 16 |
What this means if you are opening or renovating a space: Interior non-structural demo permits issued fastest. Demo is usually the first trade on site, so it is often the easiest part of the schedule to start early while the finish-out set is still in permit. See our interior demo page.
Change of use
205 permits in 2026; median 64 days from application to issue; median 2,800 square feet.
Permits by month
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov |
|---|---|---|---|---|---|---|---|---|---|---|
| 11 | 17 | 15 | 19 | 16 | 16 | 19 | 16 | 28 | 34 | 14 |
What this means if you are opening or renovating a space: Change of use had the most distinct contractors per permit. Converting a space to a new use adds steps before build-out, so send the plan check comments with the drawings when you ask for pricing. See our change of use page.
Office floor remodel
396 permits in 2026; median 49 days from application to issue; median 3,567 square feet.
Permits by month
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov |
|---|---|---|---|---|---|---|---|---|---|---|
| 56 | 32 | 35 | 38 | 25 | 33 | 39 | 48 | 21 | 47 | 22 |
What this means if you are opening or renovating a space: Office floor remodels were the largest group by count. Most happen in occupied buildings, so phasing and after-hours work belong in the quote from the start. See our office floor remodel page.
Corporate amenity
93 permits in 2026; median 83 days from application to issue; median 3,818 square feet.
Permits by month
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov |
|---|---|---|---|---|---|---|---|---|---|---|
| 5 | 12 | 10 | 10 | 15 | 7 | 8 | 8 | 5 | 10 | 3 |
What this means if you are opening or renovating a space: Break rooms, pantries, lobbies and lounges show up in steady numbers. These rooms are small but sit inside working offices, so access hours and noise windows drive the schedule. See our corporate amenity page.
Healthcare
84 permits in 2026; median 64 days from application to issue; median 2,032 square feet.
Permits by month
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov |
|---|---|---|---|---|---|---|---|---|---|---|
| 5 | 8 | 4 | 6 | 3 | 10 | 15 | 16 | 9 | 6 | 2 |
What this means if you are opening or renovating a space: Healthcare permits were the smallest by median area. Clinic and hospital work adds barrier, dust-control and phasing steps that the facility sets, so ask for those steps as separate quote lines. See our healthcare page.
Restroom and ADA
64 permits in 2026; median 79 days from application to issue; median 2,170 square feet.
Permits by month
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov |
|---|---|---|---|---|---|---|---|---|---|---|
| 3 | 2 | 1 | 4 | 6 | 6 | 5 | 25 | 7 | 5 | 0 |
What this means if you are opening or renovating a space: Restroom and accessibility upgrades are small spaces with long permit times relative to their size. Plan for the building to keep one restroom open while the other is under construction. See our restroom and ada page.
Warehouse and industrial
85 permits in 2026; median 60 days from application to issue; median 10,350 square feet.
Permits by month
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov |
|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 10 | 4 | 4 | 7 | 12 | 9 | 9 | 12 | 8 | 0 |
What this means if you are opening or renovating a space: Warehouse and industrial permits had the largest median area. The office and restroom side of a flex or warehouse bay is often built while the floor keeps running. See our warehouse and industrial page.
Planning a space in Austin?
Send the drawings, the plan check or permit number if one exists, your target date and the building access hours. We reply with questions or a written line-item quote. Call 512-689-8346 or text 512-689-8346.
Source: City of Austin Open Data, Issued Construction Permits (commercial building permits issued from 2026-01-01 on), pulled 2026-11-24. Counts and medians only; no names, permit numbers or addresses. Last updated .